Purpose

To obtain authorization to purchase a bew boiler for the Sauk County Health Care Center.

Background

Sauk County Health Care Center needs to replace one boiler.

Resolution Body

RESOLUTION NO. _____ - 2017

 

AUTHORIZING THE PURCHASE OF A HIGH EFFICIENCY BOILER FOR THE SAUK COUNTY HEALTH CARE CENTER

Text Box: Fiscal Impact: [  ] None   [ x ] Budgeted Expenditure    [  ] Not Budgeted 

Text Box: Background: The Health Care Center has had a boiler that has not functioned properly since install in 2009.  We have anticipated needing to repair or replace for several years.  Capital expense budget monies have been set aside in 2017 budget to address needing replacement.  Boiler became non-functional in late Spring 2017 and will need to be replaced prior to Fall 2017.  

 

WHEREAS, the 2017 Health Care Center Budget contains $93,000 allocated for the purchase of capital expenses of which the boiler was budgeted for; and,  

 

            WHEREAS, the Health Care Center currently needs one high efficiency boiler due to the breakdown of one of the facility’s boilers and it is essential to provide heat for the residents of the facility; and,

            WHEREAS, the Board of Trustees has examined the bids received, which are enumerated on the bottom of this resolution; and,

 

WHEREAS, after examination of the bids the Board of Trustees recommends it to be in the best interest of Sauk County to accept the bid of Pointon Heating and Air Conditioning, Inc.

 

           

            NOW, THEREFORE, BE IT RESOLVED, by the Sauk County Board of Supervisors,

met in regular session, that the Sauk County Health Care Center be and hereby is authorized to enter into contract for purchase and installment of one high efficiency Fulton Endura Model EDR-2000 boiler for a total cost of $45,675.00; and,

 

 

 

Resolution No. ____ - 2017

(AUTHORIZING THE PURCHASE OF A HIGH EFFICIENCY BOILER FOR THE SAUK COUNTY HEALTH CARE)

Page 2

 

For consideration by the Sauk County Board of Supervisors on July 18, 2017.

 

 

Respectfully submitted,

 

 

SAUK COUNTY HEALTH CARE CENTER BOARD OF TRUSTEES

 

 

 

_________________________________                  _________________________________

Henry Netzinger, Chair                                   RICHARD ‘MIKE’ FLINT

 

 

_________________________________                  _________________________________

WILLIAM HIGGINS                                            TERRI LANGER

 

 

_________________________________                  _________________________________

MARY ELLEN MURRAY                                     DENNIS POLIVKA

 

 

_________________________________

NATHAN JOHNSON

 

2017 Boiler Bids

  1. Pointon Heating and Air Conditioning Inc.-$45,675.00

  2. Thermo//Dynamics - $53,500.00

 

Fiscal Note:  Budgeted in Capital Outlay for HCC 2017 budget.