BRIDGE REPLACEMENT DESIGN

Contract Status: 
Finalization
Contract Type: 
Service
Contract Source: 
Contractor
Contract Duration (months): 
12months
Responsible Department: 
Highway
Vendor (Contractor): 
Westbrook Associated Engineers Inc.
Contract Value: 
$80000
Annual Cost: 
$0
Total Value / Impact: 
80000.00

Westbrook Associated Engineers agrees to provide the following engineering services to Sauk County Highway for the Bridge Replacement Design for CTH N Bridge over Sugar Grove Creek, P56-909 and CTH W Bridge over Seeley Creek, B-56-789 in Sauk County, WI

Review

Contract for review... wasn't sure if it needed to be reviewed or not

 

01/14/21 Rebecca reviewed and emailed Patrick with what she recommended for changes.