AUTHORIZING THE PURCHASE OF A REDUNDANT DATA STORAGE UNIT

Committee Status: 
Approved
Budget Status: 
Budgeted
Decision Impact: 
Routine
FTE Impact: 
No
Funding Source: 
Levy

Purpose

To authorize the purchase of a redundant data storage device to be installed at the backup data center in the Law Enforcement Center.

Background

Background: Sauk County’s information system utilizes a centralized network storage unit for system file storage.  For system storage redundancy, a second device is to be deployed at the Law Enforcement Center, as part of the implementation of a backup data center,

The funds for the purchase of this device were included in the MIS 2019 Capital Improvement Plan (CIP).  The plan, as approved by the CIP Committee, designates an amount of $44,763 in 2019 for this purchase.  This amount was subsequently appropriated in the 2019 MIS budget.  

Purchase of this storage unit is key in the implementation of system redundancy, safeguarding critical data and providing improved system dependability.

Budget Status (Other/External Sources): 

NOW, THEREFORE, BE IT RESOLVED, by the Sauk County Board of Supervisors met in regular session, that the following quote be and hereby is accepted by the County of Sauk; 

        Heartland Business Systems:  Dell Unity Storage System: $  34,844,74

and,

BE IT FURTHER RESOLVED, that the Management Information Systems Director is hereby delegated the authority to sign any contracts related to the purchase and installation of said equipment on behalf of Sauk County.
 
For consideration by the Sauk County Board of Supervisors on June 18, 2019
 

Requested Board Review Date: 
Tuesday, June 18, 2019